Analysis Of Risk Management In Development SMK Stikes Rajawali Bandung (Case Study: Well Foundation)
Abstract
it has a steep terrain location that creates various risks, so a risk analysis
is needed. The identification in this study was 32 risks. This research
uses qualitative and quantitative methods with the stages of identifying
possible risks, assessing risks, knowing the causes, and ways of dealing
with dominant risks if they occur. The results of the study of the 32 risks
consisted of 3 very high risks, 2 high risks, 23 medium risks and 4 low
risks. The biggest risk comes from the external risk that can be detected,
namely the risk of rain with a score of 20. Therefore, the risk of rain
requires ideal treatment using a dewatering pump.
Keywords
Full Text:
PDFReferences
Annisa, A. (2019). Management of Communication Project: Study Case Companies Based Engineering, Procurement, Construction and Manufacturing (EPCM) Region Industry Jababeka Cikarang. Planners Insight: Urban and Regional Planning Journal, 2 (1), 026-034.
Dapu, Y. C., Dundu, A. K. T., & Walangitan, D. R. (2016). Factors That Cause Cost Overrun In Construction Projects. Journal of Civil Statics, 4(10).
Dharma, AAB, Putera, IGAA, & Parami, AAD (2017). Management Risk Safety and Health Work (K3) In the Project Development Jambuluwuk Hotel & Resort. Spectran's Journal, 5 (1), 1-87.
Godfrey, PS, 1996. Control of Risk, A Guide to The Systematic Management of Risk from Construction. Connstruction Industry Research and Information Association (CIRIA). Westminster London.
Herdianto, A., Tanjungsari, A. D. R., Hidayat, A., & Hatmoko, J. U. D. (2015). Evaluation of Rework (Rework) on a Building Construction Project in Semarang. Journal of Civil Engineering Works, 4 (1), 93-106.
Hartono, Widi, etc, 2015, Risk Analysis of Upper Structure Construction Using the Analytical Hierarchy Process Method. Civil Engineering Scientific Journal, Sebelas Maret University, Surakarta.
Ismael, I., & Junaidi, J. (2014). Identification of Factors that Affect Delay Implementation of Works on Project Building in the city of Bukittinggi. Momentum Journal, 16 (1).
ISO Organization. (2018). ISO 31000:2018 Risk Management - Guidelines. Switzerland: ISO Organization
Kerzner, H. 2010. Organizing and Staffing The Project Office and Team. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 141-144.
Magna, MT, Hartono, W., & Sugiyarto, S. (2017). Construction Risk Analysisof Bore Pile Structure on Projects Using the Analytical Hierarchy Process ( Ahp ) Method. Civil Engineering Matrix, 5 (2).
Maharani, G. R. (2011). Cost and Time Risk Management On The Under Structure Work Of A High-rise Building Project In Jakarta. Thesis.
Messah , YA, Widodo, T., & Adoe , ML (2013). Study of Causes of Delays in Implementation of Building Construction Projects in Kupang City. Journal of Civil Engineering, 2 (2), 157-168.
Nugraheni, Vita Melia, 2012, Risk Analysis of the Non-Execusable Scope at the Implementation Stage of the Regional Station X Station Construction Project which Affects Changes in Project Performance, Thesis, Specific Project Management, Jakarta.
PMI. (2017). A guide to the project management body of knowledge (PMBOK) (6 th ed.). Project Management Intitute , Inc: Pennsylvania.
Soputan, G.E.,So,pie, B.F.,& Mandagi, R.J. (2014).Occupational Health Health and Safety (K3) Risk Management (Case Study of the Eben Haezar High School Building Construction). Scientific Journal of Media Engineering, 4 (4).
Standards Australia / Standards New Zealand (AS / NZ). (2004). Handbook: Risk Management Guidelines Companion to AS / NZS 4360: 2004.
Subiyanto, Eddy. (2010). Risk management lecture slides. Depok: University of Indonesia.
Suwinardi, S. (2016). Manajemen Risiko Proyek. Orbith: Majalah Ilmiah Pengembangan Rekayasa dan Sosial, 12 (3).
Utomo, ES, Putrad, RR, Chandra, HP, & Kusumastuti, C. (2019). Risk Management of Wharf Repair Construction Project in Gresik City. Journalof Civil Engineering Primary Dimensions, 8(2), 115-121.
Wulandari, M., & Listyawan, A. B. (2017). Behavior of Covered Square Footprints on Sand Due to Burden (Doctoral dissertation, Muhammadiyah University of Surakarta).
DOI: https://doi.org/10.36870/japps.v3i1.201
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Ciptaan disebarluaskan di bawah Lisensi Creative Commons Atribusi-BerbagiSerupa 4.0 Internasional.